“In Axis Surplus Ins. Co. v. Caribbean Beach Club Assn., 2014 WL 2900930 (Fla.Dist.Ct.App., June 27, 2014), a Florida court recently held that the insurer could not rely on a policy requirement that conditioned recovery of the cost of complying with current building codes during reconstruction on having completed the work within two years of the loss.  The insurer waived the two-year requirement by failing to raise it until the entire two years had elapsed and choosing to spend that time cooperating with the policyholder’s efforts to determine the necessary scope of repair instead.”